Metronet – Byford Rail Extension
The Armadale Line is being extended approximately 8km south to a new ground-level station in Byford, supporting one of the fastest growing areas in Australia. Armadale Station is being rebuilt as an elevated station with three nearby busy level crossings removed and replaced with elevated rail. Other level crossings between Armadale and Byford are also being removed with alternative treatments to improve traffic flow and ease road congestion.
FSC's Role
FSC Civils is responsible for delivering complex construction works for the viaduct, showcasing our capability in handling large-scale infrastructure projects.” to “Major subcontractor engaged by METConnx to deliver complex construction works for the viaduct, showcasing our capability in handling large-scale infrastructure projects.
Key elements included:
- 1.5 km long Armadale Station viaduct
- Station Concourse Package
- PSP Bridge
Scope of works
Precast Installation:
- Installation of precast elements, including columns, headstocks, planks, and beams.
- Execution of complex temporary works to ensure stability and safety during installation, demonstrating our proficiency in managing intricate engineering challenges.
In Situ Concrete Works:
- Construction of in situ columns, beam stitches, plank stitches, derailment kerbs, and track slabs.
- Precise grouting of structures, ensuring structural integrity and longevity.
Earthing and Bonding:
- Comprehensive execution of earthing and bonding works across the viaduct, critical for operational safety and compliance with electrical standards.
$42 million
ClientLaing O'Rourke
DurationFeb 2024 - March 2025